Shutdown Work Planning

Major work planned for upcoming shutdowns

FY16-1 - December - January 2015
  • Install straightened Linac Accelerating Structures
  • Move Sector 16 beamline B branch inboard. (tentative)
  • Install Waveguide for Linac Transverse Deflection Cavity
FY16-2 - April - May 2016
  • Install straightened Linac Accelerating Structures
  • Remove and Replace sector 4-ID Vacuum Chamber
  • Install Linac Transverse Deflection Cavity
  • Install LN2 Purge System
FY16-3 - August - September 2016
  • Install straightened Linac Accelerating Structures
  • SCU0 upgrade on 6-ID
  • Canting of 2-ID